|
Rain,
cold didn't dampen Homecoming dreams Editor-in-Chief
Crosswalk
construction continues at a steady pace for the safety of Missouri
Southern students. I
was so excited to finally break ground and see the project begin as
planned, said Dr. Terri Agee, vice president for business affairs. According
to the contract dates, the projects on Newman and Duquesne roads must be
substantially complete by Jan. 21, and final completion must occur by
Feb. 11. But
officials expect the traffic signals to be up and running well before
those dates. Agee said she believes by the time spring semester classes
begin Jan. 13, construction on the traffic signals will be nearly
complete. She said the safety barrier on Newman Road may need further
work following winter break. Bob
Harrington, physical plant director, has sooner completion in mind. I
fully expect everything to be done before the beginning of the spring
semester, he said. John
Bolte, the project engineer from Tri-State Engineering, is also thinking
positively. We
want the widening work and signals operating by Christmas, he said.
Our goal is to get this thing going before Christmas. Agee
said the construction is right on target to meet these goals.
Snyder Bridge Co., the company performing the construction, has
experienced no weather or other delays. We
haven t run into anything unexpected, Agee said. It s been
very smooth, and we re right on time. Students
feel a bit differently. The
construction seems to be going a little slowly, but I m still glad
it s happening, said Megan Scott, freshman general business major. No
additional costs have arisen. The original bid of $382,787 still stands
to cover the construction on the crosswalks. All of the equipment is
also already on-site and ready for installation. We
ordered all of that months ago so it would be here, Agee said.
We ll have no delays with that. On
Duquesne Road, two pole bases for the traffic signals were already
poured, and the other two were poured this week. A gas pipe was also
moved successfully 15 feet to the west by Missouri Gas & Energy.
Harrington said he was worried some of the trees might be destroyed by
the move, but most of them remained unharmed. The
gas company did an excellent job on that, Agee said. They
re-seeded the area and saved most of the trees. We re very pleased
with the job. Bolte
said more construction will begin on Duquesne soon. Newman
Road has been cut to prepare the road for widening, and new curbs have
been installed. The installation of drainage piping has also been
performed, the ground just has to be filled in around the piping. Due
to the construction along Newman, students and other pedestrians have
been forced to use the tunnel rather than the crosswalk. Vehicles are
also not allowed to enter the residence halls from Newman Road. They
must enter behind the halls on Duquesne. Our
goal was minimal inconvenience, but whenever there s construction,
there s always going to be inconveniences, Agee said. Scott
said the only time the detour through the tunnel has bothered her is
when the walls were being painted. The
smell was really strong, and there really wasn t another way to go
across campus, she said. Despite
the detours, Agee and Harrington said they have received no complaints.
Bolte said he has heard no complaints, either. The
students have been great, Agee said. I really appreciate the
students cooperation in using the tunnel. It s allowed the
construction project to proceed on as scheduled. Harrington said he really wanted to praise the students for their cooperation. |
![]() |
|
Bill Shepard/The Chart Dan Yates of Snyder Bridge Co. fits a piece of the new cover together at the Newman crosswalk. |